Tower Roof Update – 12

Roof Project Update  Dear Residents, Our crews are continuing work on the roof and moving steadily through the remaining phases. Thank you for your ongoing patience—these improvements will help keep the building safe and comfortable for everyone. We’ll provide another update soon. Goose Hollow Tower Management Team

Tower Roof Update – 11

Roof Project Update – Nearly Complete Dear Residents, Good news — roof work is now nearly complete! Crews are finishing up the last few sections this week & next week. You may still notice construction activity, noise, and occasional odors as workers wrap up remaining tasks and clean up the site. Thank you for your […]

Tower Roof Update – 10

Roof Project Update – Final Phase Begins Dear Residents, We’re pleased to share that the roof project is entering its final phase! This week, the construction crew will begin installing metal flashing and caps on the roof to complete the work. Please note that banging, hammering, and other construction noises are expected throughout the week […]

Tower Roof Update – 9

Construction Update – Boilers Temporarily Offline Today Dear Residents, Good news — the roof replacement project is now 90% complete! Thank you for your continued patience as we near the finish line. As part of the final work, our contractors will be relocating the building’s gas line today. This will require a temporary shutdown of […]

Tower Roof Update – 8

Construction Update – Work Continues Dear Residents, This week, roofing work continues at Goose Hollow Tower. Crews remain on-site, and you may continue to hear construction noise during daytime hours.  We appreciate your continued patience as this important project progresses. Thank you for your understanding and cooperation. Goose Hollow Tower Management Team

Tower Roof Update – 7

Roof Project Update – 50% Complete & Upcoming Crane Day Dear Residents, We’re pleased to share that the roof replacement project has reached the halfway mark — approximately 50% complete. Thank you for your continued patience and cooperation throughout this work. Please note the following:  The next crane day is scheduled for Wednesday, October 15th. […]

Tower Roof Update – 6

Notice to Residents – Roofing Project Update Dear Residents, Work on the roof project at Goose Hollow Tower is continuing this week. Please be prepared for: Noise during the day as crews carry out construction activities. Workers onsite and around the building, especially near entry points and staging areas. Ongoing roof work that may occasionally […]

Tower Roof Update – 5

Notice to Residents – Roofing Project Update Dear Residents, We want to provide you with an update on the ongoing roof replacement project at Goose Hollow Tower: •Wednesday, October 1st: The crane will return to the property for construction activity. Please be aware that parking and street access on SW Market Street may be temporarily […]

Tower Roof Update – 4

Notice to Residents – Roofing Project Update Dear Residents, We want to provide you with an update on the ongoing roof replacement project at Goose Hollow Tower: Ongoing Work: General roof demolition will continue through the end of this week. Please expect construction noise beginning at 8:00 AM daily, with crews arriving and setting up […]

Tower Roof Update – 3

Notice to Residents – Roofing Project Update   Dear Residents,   We want to provide you with an update on the ongoing roof replacement project at Goose Hollow Tower: Thursday, September 11th: The crane will return to the property for construction activity. Please be aware that parking and street access on SW Market Street will […]

Tower Roof Update – Week 2

Important Notice: Roof Work & Street Closure  Dear Goose Hollow Tower Residents, We want to keep you informed about upcoming construction activities as part of the roof replacement project. Roof Work Beginning– Starting Monday, August 25th, demolition on the roof will begin.– You should expect construction noise beginning at 8:00 AM daily throughout the week. […]

Tower Roof Update – Week 1

Notice to Goose Hollow Residents Roof Replacement Project Begins August 19th  Dear Residents,  We’re excited to announce that starting Tuesday, August 19th, the roof replacement project at Goose Hollow Tower will officially begin. This significant upgrade will enhance building, energy efficiency, and overall maintenance.  What to Expect During Phase One:  Contractors On-Site Crews will begin arriving and […]